Regulatory Citation(s):
78.85. Cementing
standards.
(f)
A copy of the cement job log shall be available at the well site for inspection
by the Department during drilling operations.
The cement job log must include…
Question:
Must
operators provide the log for all cement jobs already performed,
or just for those that had not yet been completed by February 5, 2011?
Response:
Cement
job logs need only be available for cement jobs completed after February 5, 2011.